9th Circuit Finds That FERC Acted Arbitrarily and Capriciously by Awarding Incentive Adders to PG&E for Membership in CAISO

Jan 10, 2018

Reading Time : 2 min

The court’s reasoning was straightforward. FERC stated in Order No. 679 that it “will approve, when justified, requests for ROE-based incentives for public utilities that join and/or continue to be a member of” a transmission organization.5 But FERC also stated that it would not create a “generic adder for such membership” and that it would consider incentives on a case-by-case basis.6 The justification that FERC gave for offering such incentives is that “continuing membership [in a transmission organization] is generally voluntary”7 and that such incentives would induce utilities to join, and remain members of, transmission organizations. However, as the court observed, an incentive adder “cannot ‘induce’ behavior that is already legally mandated,”8 and FERC itself has previously refused to award incentives for legally mandated behavior.9

The court concluded that FERC essentially treated ROE adders for transmission organization membership as “generic” by awarding one to PG&E without consideration of PG&E’s case-specific circumstances (i.e., that it is not free to leave CAISO). In doing so, it arbitrarily and capriciously departed without explanation from its stated policy that such adders were to be awarded on a case-by-case basis.

The 9th Circuit’s decision will have an immediate impact for both PG&E and other California utilities. For example, on December 29, 2017, FERC authorized an ROE adder for CAISO membership for Southern California Edison Company, which, like PG&E, is required to seek CPUC authorization to leave CAISO.10 The decision may also impact utilities elsewhere; FERC has routinely granted requests for ROE adders based on transmission organization membership with little consideration of case-specific factors. Thus, utilities located in other transmission organizations may find themselves in the same position as CAISO utilities, at least if state law prevents the utility from leaving the transmission organization at will.

 


1 Ca. Pub. Utils. Comm’n v. FERC, No. 16-70481, 2018 WL 315575 (9th Cir. Jan. 8, 2018) (“9th Cir. Order”).

2 Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 (“Order 679”), order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh’g, Order No. 679-B, 119 FERC ¶ 61,062 (2007).

3 Order No. 679 at P 326.

4 Id. at P 331.

5 9th Cir. Order at *5 (emphasis in original) (citing Order No. 679 at P 326) .

6 Id.

7 Order No. 679 at P 331.

8 9th Cir. Order at *5.

9 Id. at *7.

10 See S. Cal. Edison Co., 161 FERC ¶ 61,309 (2017).

Share This Insight

Previous Entries

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

Speaking Energy

January 23, 2025

Under a second Trump presidency, the U.S. is expected to consider reversal of many of the Biden administration’s climate and environmental policies, in addition to a markedly different approach to trade policy and oil & gas regulation. This includes expanding oil & gas development on public lands and offshore, lifting the pause on liquified natural gas (LNG) exports to non-Free Trade Agreement countries and repealing the methane fee.

...

Read More

Speaking Energy

January 15, 2025

We are pleased to share a recording of Akin’s recently presented webinar, “Drilling Down: What Oil & Gas Companies Can Expect from Federal Agencies During Trump’s Second Administration.”

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.