As Bankruptcy Bells Ring in the Outer Continental Shelf, BSEE May Toll for You

Sep 30, 2019

Reading Time : 4 min

Why Is This Happening?

In a perfect world, parties that own and operate offshore assets would be responsible to decommission them as the need arises. Increasingly, however, lessees and operators are finding themselves without the financial wherewithal to conduct the expensive decommissioning, and either declare bankruptcy or otherwise successfully abandon their interests in uneconomical wells and related infrastructure. BSEE then is left to find alternative funding, and looks to parties with less direct interests for decommissioning so taxpayers are not left footing the bill.

The Outer Continental Shelf Lands Act (OCSLA) gives BSEE broad authority to administer offshore oil and gas leasing and production.3 Pursuant to OCSLA, BSEE regulations impose decommissioning obligations on any party that:

  • Drills a well.
  • Installs a platform, pipeline or other facility.
  • Creates an obstruction to other users of the outer continental shelf.
  • Is or becomes a lessee or the owner of operating rights of a lease on which there is a well that has not been permanently plugged[,] a platform, a lease term pipeline, or other facility or an obstruction.
  • Is or becomes the holder of a pipeline right-of-way on which there is a pipeline, platform, other facility or an obstruction.
  • Re-enters a well that was previously plugged.4

OK, But Why Is This Happening More?

In the most recent years for which data is available, BSEE has overseen the removal of, on average, more than 200 structures per year from the Gulf of Mexico alone.5 BSEE estimates that approximately 3,000 active platforms exist under its jurisdiction, 40 percent of which are over 25 years old and in line to be removed in the near future.6 As oil and gas production declines, the number of oil and gas infrastructure removals continues to rise.

Compounding the shear increase in numbers, oil and gas companies are declaring bankruptcy at rising rates with no apparent end in sight.7 Twenty-six North American exploration and production companies have filed for bankruptcy in 2019 to date, following two consecutive years of more than 20 bankruptcies.8 BSEE, meanwhile, responds to these bankruptcies by exerting its authority under OCSLA to hold non-bankrupt predecessor parties responsible for decommissioning costs, including those who operated the facilities but also those who merely held leasehold or right-of-way interests.9 Because the decommissioning regulations impose joint and several liability, all parties who accrue decommissioning obligations can be forced to pay these costs, regardless of the remoteness of their link to a given structure.10

So What Do I Do After (or Better Yet Before) BSEE Comes Knocking?

Although the current administration’s general deregulatory stance may suggest otherwise, BSEE has given no indication that it intends to curtail its recent trend of enforcement.11 If anything, it may expand its authority to new parties and maybe even new places, like the Pacific Ocean.12 As such, any party with offshore interests in those areas should begin planning now for how to both prepare for and respond to a future Order to Decommission.

First, parties with offshore interests likely to face Orders to Decommission should assess their available legal defenses, including those based on statutes of limitations, divisibility and BSEE policy setting forth the appropriate order and priority of payees. Then, if and when an Order comes in, the party should determine the costs and benefits of an appeal. Time is of the essence in negotiating with BSEE during the highly regulated administrative appeal process. And, given the difficulty in defending these suits because of advantages the law gives to BSEE, the party should assess the availability of alternative funding sources. This may mean asserting claims for decommissioning costs in bankruptcy proceedings involving parties who hold or previously held interests in the relevant assets.

In a world with dwindling oil and gas prices and rising numbers of bankruptcies, it is critical that parties with offshore interests take commonsense steps now to protect their interests and minimize their future exposure before—and after—BSEE comes knocking.


1 Akin Gump, Check Your Mail: BSEE Inviting All of Its Friends to Pay for GOM Decommissioning, Akin Gump Speaking Energy Blog (May 15, 2014), https://www.akingump.com/en/experience/industries/energy/speaking-energy/check-your-mail-bsee-inviting-all-of-its-friends-to-pay-for-gom.html.

2 Id.

3 43 U.S.C. § 1334(a).

4 30 C.F.R. § 250.1702.

5 Bur. of Safety and Envtl. Enforcement, U.S. Dept. of the Interior, Statistics for Decommissioned Platforms on the OCS (Sept. 19, 2017), https://www.bsee.gov/what-we-do/environmental-focuses/decommissioning/decommissioning-statistics.

6 Bur. of Safety and Envtl. Enforcement, U.S. Dept. of the Interior, Decommissioning, https://www.bsee.gov/what-we-do/research/tap-categories/decommissioning.

7 Jamison Cocklin, E&P Bankruptcies on the Rise as Operators Again Confront Low Oil, NatGas Prices, Natural Gas Intelligence (Aug. 15, 2019), https://www.naturalgasintel.com/articles/119296-ep-bankruptcies-on-the-rise-as-operators-again-confront-low-oil-natgas-prices.

8 Id.

9 30 C.F.R. § 250.1701.

10 Id.

11 Oil and Gas and Sulfur Operations in the Outer Continental Shelf-Request for Information Regarding Potential Impacts of Decommissioning-in-Place of Pipeline-Related Infrastructure in Deepwater, 83 Fed. Reg. 67343 (Dec. 28, 2018).

12 Memorandum regarding The Bureau of Safety and Environmental Enforcement’s Decommissioning Program Assignment No. 2016-EAU-062, Office of Inspector General, U.S. Dept. of the Interior (March 26, 2019), https://www.doioig.gov/sites/doioig.gov/files/CloseoutMemo_BSEEDecomissioning_040119.pdf.

Share This Insight

Previous Entries

Speaking Energy

December 5, 2024

On November 27, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued Venture Global CP2 LNG, LLC,1 an order that sets aside, in part, the Commission’s prior authorization of the CP2 LNG Terminal and CP Express Pipeline Project (collectively, the CP2 Project) under sections 3 and 7 of the Natural Gas Act (NGA). In anticipation of future appellate challenges to its authorization of the CP2 Project, FERC ordered the initiation of a supplemental environmental impact statement (SEIS) process under the National Environmental Policy Act (NEPA) to assess the CP2 Project’s contribution to cumulative air impacts for nitrogen dioxide (NO2) and particulate matter less than 2.5 micrometers (PM2.5). Accordingly, FERC stated that it would not allow construction to commence on the CP2 Project’s proposed liquefied natural gas (LNG) export terminal and related feed gas pipeline until the SEIS process concluded and a subsequent order was issued. Concurrent with its Venture Global order, FERC issued a projected schedule for the NEPA process that does not conclude until July 24, 2025. Construction on the CP2 Project had been expected to be imminent, with the project sponsor seeking a partial authorization to proceed with construction only hours prior to Venture Global’s issuance.

...

Read More

Speaking Energy

December 5, 2024

On November 27, 2024, in Venture Global, CP2 LNG, LLC,1 the Federal Energy Regulatory Commission’s (FERC or Commission) explicitly overruled precedent set in Northern Natural Gas Co.,2 a 2021 decision in which FERC made an affirmative finding that an interstate natural gas pipeline project it was certificating under section 7 of the Natural Gas Act (NGA) would not make a “significant” contribution to global climate change. Northern Natural is the only FERC decision in which a so-called significance determination was made with respect to greenhouse gas emissions (GHG) arising from a FERC-regulated natural gas infrastructure project. In Venture Global, FERC rejected arguments that it needed to follow Northern Natural and assess the significance of GHG emissions in all NGA certificate proceedings to comply with the National Environmental Policy Act (NEPA). NEPA requires federal agencies, including FERC, that perform “major federal actions,” which include issuing NGA section 7 certificates, to prepare an environmental impact statement (EIS) if the action will “significantly affect[] the quality of the human environment.”3 FERC has been under pressure to fully explain why it has chosen not to apply Northern Natural’s significance analysis in subsequent cases, and that issue is currently before FERC on remand from the U.S. Court of Appeals for the District of Columbia (D.C. Circuit) in Healthy Gulf et al. v. FERC, which reviewed FERC’s approval of a liquefied natural gas (LNG) terminal under NGA section 3.

...

Read More

Speaking Energy

December 4, 2024

On November 21, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued Order No. 1920-A1 addressing requests for rehearing and clarification of FERC’s landmark final rule on transmission planning and cost allocation issued in May 2024. While the Commission largely affirmed the final rule, the order grants rehearing of some of the more controversial aspects of Order No. 1920.

...

Read More

Speaking Energy

November 26, 2024

We are pleased to share a recording of Akin’s recently presented webinar, “Post-Election Outlook for the Energy Sector.”

...

Read More

Speaking Energy

August 7, 2024

*Thank you to JaKell Larson, 2024 Akin Summer Associate, for her valuable collaboration on this article.

...

Read More

Speaking Energy

July 31, 2024

Interstate oil, liquid and refined products pipelines regulated by the Federal Energy Regulatory Commission (FERC) will soon be able to raise their transportation rates (provided they were set using FERC’s popular Index rate methodology) in the wake of a significant new decision by the District of Columbia Circuit (the D.C. Circuit) in Liquid Energy Pipeline Association v. FERC (LEPA).

...

Read More

Speaking Energy

July 29, 2024

On Wednesday, July 24, 2024, the U.S. House of Representative Committee on Energy and Commerce held a Subcommittee on Energy, Climate, and Grid Security hearing to review the Federal Energy Regulatory Commission (FERC or Commission) Fiscal Year 2025 Budget Request. Members of the Subcommittee had the opportunity to hear testimony from all five Commissioners, including FERC Chairman Willie Phillips and Commissioner Mark Christie, as well as the three recently confirmed commissioners, David Rosner, Lindsay See and Judy Chang. In addition to their prepared remarks, the five commissioners answered questions on FERC’s mandate to provide affordable and reliable electricity and natural gas services nationwide, while also ensuring it fulfills its primary mission of maintaining just and reasonable rates.

...

Read More

Speaking Energy

July 29, 2024

On July 9, 2024, the U.S. Court of the Appeals for the D.C. Circuit held that the Federal Energy Regulatory Commission (FERC or the Commission) erred in ordering refunds for certain bilateral spot market transactions in the Western Energy Coordinating Council (WECC) region that exceeded the $1,000/megawatt-hour (MWh) “soft” price cap for such sales.1 Finding FERC failed to conduct a “Mobile-Sierra public-interest analysis” before “altering” those contracts by ordering refunds, the court vacated FERC’s orders and remanded the case to FERC for further proceedings.2

...

Read More

© 2024 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.