Electric Cooperatives Seek FERC Determination on PURPA Preemption of Maryland’s Community Solar Program

Sep 7, 2016

Reading Time : 3 min

By: Shawn Whites, (Paralegal)

Under Maryland’s community solar program, electric utilities are required to compensate community solar generators for the power produced in excess of the generator’s needs, effectively purchasing and taking title to the power. The utilities must then “use” that excess power. As the cooperatives explain in their Petition, in order to use such power, an electric utility must sell it to others. The cooperatives then conclude that, because they are reselling the power, the original purchase of the excess generation must constitute a wholesale sale under the FPA, under which FERC has exclusive jurisdiction.

The cooperatives recognize that Section 210 of PURPA provides states with the authority to establish wholesale rates if the electric generator is a qualifying facility (QF). However, PURPA requires that the state set wholesale rates no higher than a utility’s avoided costs. Hence the issue: if the MPSC’s regulations require that an electric utility use, or purchase, the excess power of a community solar generator—a “wholesale” sale—then that generator must be a QF, and the rates for the sale must be less than or equivalent to the cooperative’s avoided costs. If the generator is not a QF, then the MPSC lacks jurisdiction to set the rates for a wholesale sale, because only FERC has the authority to set wholesale rates for non-QF generators. The cooperatives argue, however, that neither the community solar statute nor the MPSC’s regulations “contain an express requirement that a [community solar generator] must be a QF.”

If FERC determines that a generator participating in Maryland’s community solar program must be a QF, then the cooperatives state that the next step is to ensure that they are purchasing the excess power at their avoided cost, as set forth by PURPA.1  Instead, they argue, the current MPSC regulations are ambiguous as to whether or not the costs paid for excess generation would exceed the avoided costs. As the MPSC regulations are written, “an electric company shall pay a subscriber [of the program] a dollar amount of excess generation as reasonably adjusted to exclude the distribution, transmission, and non-commodity portion of the customer’s bill unless the electric company records subscriber credits as kilowatt hours.”2 While the first half of the text, by nature of “excluding” wires-related costs, implies a rate that could be less than or equal to the cooperatives’ avoided costs, the cooperatives take issue with the italicized portion of the regulation, claiming that it “sets payments potentially at a level other than the actual avoided costs at the time of delivery,” thus “creat[ing] an exception to the avoided cost standard under PURPA.”  The cooperatives’ solution is to simply add language to the MPSC regulations mirroring the language of PURPA, noting that it is well within the authority of the MPSC to do so.

The cooperatives lastly note that the MPSC regulations are at odds with the language of the community solar program’s statute, which states that excess generation “shall be purchased under the [utility’s] process for purchasing the output from qualifying facilities at the amount it would have cost the electric company to procure the energy,”3 or, simply put, the avoided cost. Since the statute is compliant with the standards of PURPA, the cooperatives argue that the MPSC regulations could be revised to comply with their own statute, as well as federal law.

The Petition comes shortly after FERC reviewed PURPA’s provisions on mandatory purchase obligations and avoided cost calculations at a June 29, 2016, technical conference and further highlights the growing tension between the federal and state jurisdiction of electricity sales.4 Depending on the outcome of FERC’s ruling on the Petition, the case could have large effects on the growing number of state-implemented community solar programs, particularly on the ways in which state regulatory authorities establish the costs for purchases of excess generation in compliance with PURPA.


1  “Avoided costs” are the costs that the cooperatives would have paid either to generate the electricity themselves or purchase it from another source.

2  18 C.F.R. § 292.304(a)(2).

3  Md. Code Regs. 20.62.02.07A.

4  Md. Code Ann., Pub. Util. § 7-306.2(d)(7).

5  See our blogs on federal & state jurisdictional issues here and here.

Share This Insight

Previous Entries

Speaking Energy

August 07, 2024

*Thank you to JaKell Larson, 2024 Akin Summer Associate, for her valuable collaboration on this article.

...

Read More

Speaking Energy

July 31, 2024

Interstate oil, liquid and refined products pipelines regulated by the Federal Energy Regulatory Commission (FERC) will soon be able to raise their transportation rates (provided they were set using FERC’s popular Index rate methodology) in the wake of a significant new decision by the District of Columbia Circuit (the D.C. Circuit) in Liquid Energy Pipeline Association v. FERC (LEPA).

...

Read More

Speaking Energy

July 29, 2024

On Wednesday, July 24, 2024, the U.S. House of Representative Committee on Energy and Commerce held a Subcommittee on Energy, Climate, and Grid Security hearing to review the Federal Energy Regulatory Commission (FERC or Commission) Fiscal Year 2025 Budget Request. Members of the Subcommittee had the opportunity to hear testimony from all five Commissioners, including FERC Chairman Willie Phillips and Commissioner Mark Christie, as well as the three recently confirmed commissioners, David Rosner, Lindsay See and Judy Chang. In addition to their prepared remarks, the five commissioners answered questions on FERC’s mandate to provide affordable and reliable electricity and natural gas services nationwide, while also ensuring it fulfills its primary mission of maintaining just and reasonable rates.

...

Read More

Speaking Energy

July 29, 2024

On July 9, 2024, the U.S. Court of the Appeals for the D.C. Circuit held that the Federal Energy Regulatory Commission (FERC or the Commission) erred in ordering refunds for certain bilateral spot market transactions in the Western Energy Coordinating Council (WECC) region that exceeded the $1,000/megawatt-hour (MWh) “soft” price cap for such sales.1 Finding FERC failed to conduct a “Mobile-Sierra public-interest analysis” before “altering” those contracts by ordering refunds, the court vacated FERC’s orders and remanded the case to FERC for further proceedings.2

...

Read More

Speaking Energy

July 8, 2024

On June 28, 2024, in Loper Bright Enterprises v. Raimondo, the U.S. Supreme Court overruled Chevron U.S.A. Inc. v. Natural Resources Defense Council, Inc., which for 40 years required court deference to reasonable agency interpretations of federal statutes in certain circumstances, even when the reviewing court would read the statute differently. The Court ended “Chevron deference” and held that courts “must exercise their independent judgment in deciding whether an agency has acted within its statutory authority.” In doing so, the Court upended a longstanding principle of administrative law that is likely to make agency decisions more susceptible to challenge in the courts.

...

Read More

Speaking Energy

July 3, 2024

We are pleased to share a recording of Akin and ICF’s recently presented “Powering Progress: Decoding FERC Order No. 1920” webinar, along with the program materials.

...

Read More

Speaking Energy

June 12, 2024

Join projects & energy transition partner Ben Reiter at Infocast's Transmission & Interconnection Summit, where he will moderate the “Dealing with the Impacts of Increased Interconnection Request Requirements and Costs” panel.

...

Read More

Speaking Energy

June 4, 2024

Join projects & energy transition partners Hayden Harms and Vanessa Wilson at Infocast's RNG & SAF Capital Markets Summit, where Hayden will moderate the "Investor Perspectives: Private Equity, Infrastructure Funds, & Strategies" panel, and Vanessa will moderate the "Opportunities in Other Biogas/Fuels Markets" panel.

...

Read More

© 2024 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.