FERC Staff Questions Wind Farms on Calculation of PURPA’s One-Mile Rule

Jun 21, 2017

Reading Time : 5 min

By: Shawn Whites

One-Mile Rule

Under PURPA’s “mandatory purchase obligation,” a public utility is generally required to purchase all of the output of QFs with which it is interconnected at the utility’s avoided cost rate. A facility qualifies as a QF if its capacity is less than 80 MW, which includes the aggregated capacity of other small generation facilities that (i) use the same resource type, (ii) are owned by the same person or its affiliates, and (iii) are located at the same site.1In determining whether two or more facilities are located at the same site, FERC’s regulations specify that a facility “located within one mile of the facility for which [QF status] is sought”—as measured by the distance between the electric generating equipment of the facilities—is deemed to be “located at the same site.”2Since developers often pursue multiple projects within the same general vicinity, two 80 MW facilities owned by affiliates would not qualify as separate QFs if they are located within one mile of each other. 

Beaver Creek’s Weighted Geographic Center Methodology

On February 9, 2017, Beaver Creek applied for QF status for two approximately 80 MW wind projects in Montana made up of 32 wind turbines each. Beaver Creek notes that the projects are contiguous to two additional 80 MW wind projects, although the two Beaver Creek projects are not affiliated with each other or the other two projects.3Despite their stated non affiliation, Beaver Creek nonetheless acknowledges that “the [close] proximity of these four wind projects raises a question of how the calculation of the . . . one-mile rule would be applied [if] the Commission determined that the [projects] were affiliated” or if the Beaver Creek projects decide at a later date to form an affiliate relationship.4

While the distance between the projects’ electric generating equipment (i.e., wind turbines) serves as the relevant measurement for applying the one-mile rule, Beaver Creek argues that such an approach poses a “unique challenge” for wind projects. Unlike other renewable energy projects with less stringent siting requirements and fewer pieces of generating equipment, Beaver Creek notes that the siting of wind projects is “determined based on the specific topography of the region”5in order to maximize the wind resource, which requires the dispersal of multiple wind turbines across a large stretch of land. Beaver Creek instead proposes that the “appropriate application of the one-mile rule to wind facilities is to apply the distance calculation to the weighted geographic center of the turbine array,”6since each individual wind turbine forms a piece of the project as a whole, ultimately “converg[ing] to a central point for collection.”7Beaver Creek notes that, when measuring from this geographic center, each of the projects satisfies the one-mile rule.

NorthWestern Corporation, the utility required to purchase the output of the projects, protested the proposed methodology, arguing that the one-mile rule is “unambiguous”—the electric generating equipment is the wind turbines, and the distance between the two closest turbines is less than one mile.8

Beaver Creek’s Responses to FERC’s Deficiency Letters

FERC’s deficiency letters asked Beaver Creek to (1) explain how its weighted geographic center calculation of the one-mile rule complies with the Commission’s requirement that the “distances [between two facilities] shall be measured from the electrical generating equipment of a facility,” (2) provide the distance between the wind projects by measuring the distance between the two closest individual wind turbines and (3) submit a topographical map depicting the location of each individual wind turbine.9

In its June 9, 2017, response,  Beaver Creek repeats many of the same arguments made in its original application, stressing that “measur[ing] the distance between wind generation facilities” using individual wind turbines “is an impractical view on what constitutes the ‘facility’ or ‘electrical generating equipment’ for purposes of applying” the one-mile rule.10Beaver Creek then notes that, since the “Commission has provided little guidance on how to calculate the distance between wind generation facilities for purposes of calculating the one-mile rule,”11the weighted geographic center methodology serves as a reasonable proxy that is easily applicable to all wind projects. Crucial to Beaver Creek’s argument is the fact that, when taking into account the 2.5 MW capacity of each individual wind turbine, “there is no area within a one-mile radius of [each of the projects] with more than 80 MW of generation capacity.”12

Implications

Beaver Creek is essentially asking the Commission to re interpret the one-mile rule. In previous orders on QF applications, the Commission took the position that the one-mile rule is a “rule and not a rebuttable presumption” in response to protests that two projects technically greater than one-mile apart should nonetheless fail the test because they “gamed” PURPA.13Though that context differs from the instant case, which involves the standard of measurement for applying the rule, the Commission’s language appears to be clear—the one-mile rule is not open to interpretation. 

Concerns over PURPA’s one-mile rule were most recently discussed at a June 2016 FERC technical conference, where at least one participant, the American Wind Energy Association, urged the Commission to “publish information about how it measures one mile.”14Such information has yet to be published, though it could come through the issuance of an order on Beaver Creek’s applications once quorum is restored at FERC. The future Commission will thus need to determine whether the use of a weighted geographical center methodology is an acceptable approach for calculating the one-mile rule or whether the rule’s standard of measuring from the “electric generating equipment” is also a bright line. In any event, a clarification of the Commission’s policy regarding the one-mile rule will provide increased regulatory certainty for developers of projects hoping to achieve QF status.

 


 

118 C.F.R. § 292.204(a)(1) (2017).

2Id. § 292.204(a)(2).

3The additional projects are Beaver Creek Wind , LLC and Beaver Creek Wind IV, LLC, together with Beaver Creek Wind II, LLC and Beaver Creek Wind III, LLC.  

4Beaver Creek Wind II, LLC, Application for Certification, QF17-673-000, at 12 (filed Feb. 9, 2017).  While two applications were submitted in two separate dockets, both applications are substantively the same and are therefore referred to as one application in this post.

5Id. at 13.

6Id. at 12.

7Beaver Creek Wind II, LLC, Motion for Leave to Answer and Answer, Docket No. QF17-673-000, at 5 (filed Mar. 17, 2017).

8NorthWestern Corp., Motion to Intervene, Motion to Consolidate, and Protest, Docket No. QF17-673-000, at 6 (filed Mar. 2, 2017).

9FERC Staff, Deficiency Letter, Docket No. QF17-673-000, at 2 (May 10, 2017).

10Response of Beaver Creek Wind II, LLC to May 10, 2017 Deficiency Letter, Docket No. QF17-673-000, at 3 (filed June 9, 2017).

11Id.  

12Id. at 5.

13See, e.g., DeWind Novus, LLC, 139 FERC ¶ 61,201, at P 25 (2012).

14American Wind Energy Association, Post-Technical Conference Comments, AD16-16-000, at 6 (filed Nov. 15, 2016). 

 

Share This Insight

Previous Entries

Speaking Energy

January 15, 2025

We are pleased to share a recording of Akin’s recently presented webinar, “Drilling Down: What Oil & Gas Companies Can Expect from Federal Agencies During Trump’s Second Administration.”

...

Read More

Speaking Energy

January 9, 2025

On January 6, 2025, the Federal Energy Regulatory Commission (FERC) issued a Final Rule to amend its regulations governing the maximum civil monetary penalties assessable for violations of statutes, rules and orders within FERC’s jurisdiction. The Final Rule is a result of the Federal Civil Penalties Inflation Adjustment Act Improvements Act of 2015, which requires each federal agency to issue an annual inflation adjustment by January 15 for each civil monetary penalty provided by law within the agency’s jurisdiction. The adjustments in the Final Rule represent an increase of approximately 2.6% for each covered maximum penalty. FERC’s adjusted maximum penalty amounts, which will apply at the time of assessment of a civil penalty regardless of the date on which the violation occurred, are set forth here and will become effective upon publication in the Federal Register.

...

Read More

Speaking Energy

January 9, 2025

Join projects & energy transition partners Ike Emehelu and Shariff Barakat as well as climate change partner Ken Markowitz at Infocast's Projects & Money, where Ike will moderate the "The State of Project Finance – View from the C-Suite" panel, and Shariff will moderate the "Capital Markets & Other Capital Sources for Project Finance & Investment" panel. Ken will moderate the “Carbon Markets Forecast for 2025” panel.

...

Read More

Speaking Energy

January 8, 2025

On December 16, 2024, the Federal Energy Regulatory Commission (FERC or the Commission) issued an Order to Show Cause and Notice of Proposed Penalty proposing to assess staggering civil penalties against American Efficient, LLC and its affiliates (collectively, American Efficient) in connection with an alleged scheme to manipulate the capacity markets operated by PJM Interconnection, L.L.C. (PJM) and the Midcontinent Independent System Operator, Inc. (MISO).1 The Order directs American Efficient to show cause as to why it should not be required to pay a civil penalty of $722 million and disgorge $253 million.2

...

Read More

Speaking Energy

December 5, 2024

On November 27, 2024, the Federal Energy Regulatory Commission issued Venture Global CP2 LNG, LLC, an order that sets aside, in part, the Commission’s prior authorization of the CP2 LNG Terminal and CP Express Pipeline Project (collectively, the CP2 Project) under sections 3 and 7 of the Natural Gas Act (NGA). 

...

Read More

Speaking Energy

December 5, 2024

On November 27, 2024, in Venture Global, CP2 LNG, LLC,1 the Federal Energy Regulatory Commission’s (FERC or Commission) explicitly overruled precedent set in Northern Natural Gas Co.,2 a 2021 decision in which FERC made an affirmative finding that an interstate natural gas pipeline project it was certificating under section 7 of the Natural Gas Act (NGA) would not make a “significant” contribution to global climate change. Northern Natural is the only FERC decision in which a so-called significance determination was made with respect to greenhouse gas emissions (GHG) arising from a FERC-regulated natural gas infrastructure project. In Venture Global, FERC rejected arguments that it needed to follow Northern Natural and assess the significance of GHG emissions in all NGA certificate proceedings to comply with the National Environmental Policy Act (NEPA). NEPA requires federal agencies, including FERC, that perform “major federal actions,” which include issuing NGA section 7 certificates, to prepare an environmental impact statement (EIS) if the action will “significantly affect[] the quality of the human environment.”3 FERC has been under pressure to fully explain why it has chosen not to apply Northern Natural’s significance analysis in subsequent cases, and that issue is currently before FERC on remand from the U.S. Court of Appeals for the District of Columbia (D.C. Circuit) in Healthy Gulf et al. v. FERC, which reviewed FERC’s approval of a liquefied natural gas (LNG) terminal under NGA section 3.

...

Read More

Speaking Energy

December 4, 2024

On November 21, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued Order No. 1920-A1 addressing requests for rehearing and clarification of FERC’s landmark final rule on transmission planning and cost allocation issued in May 2024. While the Commission largely affirmed the final rule, the order grants rehearing of some of the more controversial aspects of Order No. 1920.

...

Read More

Speaking Energy

November 26, 2024

We are pleased to share a recording of Akin’s recently presented webinar, “Post-Election Outlook for the Energy Sector.”

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.