DC Circuit Upholds FERC Orders on Weymouth Compressor Station

Jul 24, 2023

Reading Time : 4 min

In Fore River Residents Against the Compressor Station v. FERC,1 decided on July 21, 2023, the U.S. Court of Appeals for the District of Columbia Circuit ended long-running litigation over the Federal Energy Regulatory Commission’s (FERC or “Commission”) approval of the Weymouth Compressor Station in Norfolk, Massachusetts. The Weymouth Compressor Station is part of the Algonquin Gas Transmission, LLC and Maritimes & Northeast Pipeline, L.L.C. Atlantic Bridge Project, which received a certificate under section 7 of the Natural Gas Act (NGA) from FERC in 2017 (Docket No. CP16-9).2 In Fore River, the court found that the petitioners, local residents, municipalities, and an environmental organization lacked Article III standing to challenge two orders issued by FERC after the certificate issued (1) a December 26, 2018, delegated order granting Algonquin a two-year extension of time to construct the facilities (the “Extension Order”)3 that was subsequently upheld by a full Commission order on February 21, 2020 (the “2020 Rehearing Order”);4 and (2) a January 20, 2022, denial of rehearing (the “2022 Rehearing Order”)5 of a September 24, 2020, order authorizing Algonquin to place the facilities in service (the “In-Service Extension Order”).6 It also dismissed the petitions as moot. 

With regard to the Extension Order challenge, the court explained that the petitioners’ procedural challenges failed the “redressability prong” of Article III standing. The court explained that even if the Extension Order had been procedurally improper, the 2020 Rehearing Order fully cured any perceived defect because FERC issued it following extensive briefing. Moreover, without a procedural injury the case was moot because the court was unable to provide an effective remedy, given that the petitioners had already received additional process.

The court also found procedural flaws with the petitioners’ 2022 Rehearing Order challenge, primarily because that challenge was limited to the Rehearing Order and not the underlying In-Service Extension Order, or a subsequent denial of rehearing that was entered by default on November 23, 2020. The court relied on section 19 of the NGA, which governs appellate review of FERC orders, to hold that an order denying rehearing, standing alone, cannot be a basis for judicial review. The exception, which did not apply here, is when the order on rehearing substantively modifies the result reached in the original order. Moreover, were the 2022 Rehearing Order a reviewable order under NGA section 19, the petitioners would have needed to seek rehearing at FERC prior to petitioning the court for review. They did not. Judge Patricia Millett authored the Fore River opinion, in addition to authoring another landmark case decided in 2020 interpreting NGA section 19, Allegheny Defense Project v. FERC.7

The Fore River case is notable in large part because of the attention paid to the Weymouth Compressor Station, which faced significant litigation due to actions taken by FERC after the certificate order issued. Specifically, the 2022 Rehearing Order followed an unprecedented split-decision by FERC to reconsider the facility’s certificate order and accept briefing in February 2021 on whether to permit the Weymouth Compressor Station to remain in service. FERC was responding in large part to environmental justice concerns arising after the facility released large volumes of natural gas, referred to in industry parlance as “blowdowns,” pursuant to two emergency shutdown procedures initiated to comply with U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration (PHMSA) regulations. The additional process was cheered by some in the environmental justice community, but drew fierce criticism in dissents by Commissioners Mark Christie and James Danly on grounds that FERC was acting outside of its statutory authority and resulted in over 100 comments and briefs filed by a diverse group of pipeline industry members and advocates, environmental nongovernmental organizations and consumer groups, and former FERC commissioners as well as requests for rehearing by the affected pipeline and four individual trade associations representing pipeline operators, investors and shippers. Many of these comments questioned whether FERC was interfering with PHMSA’s pipeline safety regulations. As Akin noted in a prior client alert, PHMSA is currently accepting comments on whether to revise its regulations around blowdowns and other types of intentional releases of natural gas.

Fore River is also notable given that the project was designed to alleviate capacity constraints in the New England region, a particularly challenging place to construct natural gas infrastructure.


1 No. 22-1146 (D.C. Circ. Jul. 21, 2023) (“Fore River”).

2 Algonquin Gas Transmission, LLC, 158 FERC ¶ 61,061, order denying reh’g, 161 FERC ¶ 61,255 (2017), aff’d sub nom., Town of Weymouth v. FERC, No. 17-1135, 2018 WL 6921213, at *1 (D.C. Cir. Dec. 27, 2018) (unpublished opinion).

3 Approval for Extension of Time to Complete Project, CP16-9-000 (Dec. 26, 2018).

4 Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144 (2020).

5 Algonquin Gas Transmission, LLC, 178 FERC ¶ 61,029 (2022).

6 Algonquin Gas Transmission, LLC, Docket No. CP16-9-000 (Sept. 24, 2020) (delegated order).

7 964 F.3d 1, 16–17 (D.C. Cir. 2020) (en banc).

Share This Insight

Previous Entries

Speaking Energy

August 07, 2024

*Thank you to JaKell Larson, 2024 Akin Summer Associate, for her valuable collaboration on this article.

...

Read More

Speaking Energy

July 31, 2024

Interstate oil, liquid and refined products pipelines regulated by the Federal Energy Regulatory Commission (FERC) will soon be able to raise their transportation rates (provided they were set using FERC’s popular Index rate methodology) in the wake of a significant new decision by the District of Columbia Circuit (the D.C. Circuit) in Liquid Energy Pipeline Association v. FERC (LEPA).

...

Read More

Speaking Energy

July 29, 2024

On Wednesday, July 24, 2024, the U.S. House of Representative Committee on Energy and Commerce held a Subcommittee on Energy, Climate, and Grid Security hearing to review the Federal Energy Regulatory Commission (FERC or Commission) Fiscal Year 2025 Budget Request. Members of the Subcommittee had the opportunity to hear testimony from all five Commissioners, including FERC Chairman Willie Phillips and Commissioner Mark Christie, as well as the three recently confirmed commissioners, David Rosner, Lindsay See and Judy Chang. In addition to their prepared remarks, the five commissioners answered questions on FERC’s mandate to provide affordable and reliable electricity and natural gas services nationwide, while also ensuring it fulfills its primary mission of maintaining just and reasonable rates.

...

Read More

Speaking Energy

July 29, 2024

On July 9, 2024, the U.S. Court of the Appeals for the D.C. Circuit held that the Federal Energy Regulatory Commission (FERC or the Commission) erred in ordering refunds for certain bilateral spot market transactions in the Western Energy Coordinating Council (WECC) region that exceeded the $1,000/megawatt-hour (MWh) “soft” price cap for such sales.1 Finding FERC failed to conduct a “Mobile-Sierra public-interest analysis” before “altering” those contracts by ordering refunds, the court vacated FERC’s orders and remanded the case to FERC for further proceedings.2

...

Read More

Speaking Energy

July 8, 2024

On June 28, 2024, in Loper Bright Enterprises v. Raimondo, the U.S. Supreme Court overruled Chevron U.S.A. Inc. v. Natural Resources Defense Council, Inc., which for 40 years required court deference to reasonable agency interpretations of federal statutes in certain circumstances, even when the reviewing court would read the statute differently. The Court ended “Chevron deference” and held that courts “must exercise their independent judgment in deciding whether an agency has acted within its statutory authority.” In doing so, the Court upended a longstanding principle of administrative law that is likely to make agency decisions more susceptible to challenge in the courts.

...

Read More

Speaking Energy

July 3, 2024

We are pleased to share a recording of Akin and ICF’s recently presented “Powering Progress: Decoding FERC Order No. 1920” webinar, along with the program materials.

...

Read More

Speaking Energy

June 12, 2024

Join projects & energy transition partner Ben Reiter at Infocast's Transmission & Interconnection Summit, where he will moderate the “Dealing with the Impacts of Increased Interconnection Request Requirements and Costs” panel.

...

Read More

Speaking Energy

June 4, 2024

Join projects & energy transition partners Hayden Harms and Vanessa Wilson at Infocast's RNG & SAF Capital Markets Summit, where Hayden will moderate the "Investor Perspectives: Private Equity, Infrastructure Funds, & Strategies" panel, and Vanessa will moderate the "Opportunities in Other Biogas/Fuels Markets" panel.

...

Read More

© 2024 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.