FERC Adopts New Regulations Allowing Higher-Priced Energy Offers in Organized Electricity Markets

Nov 21, 2016

Reading Time : 3 min

As we previously reported, in January of this year, FERC proposed to require each RTO/ISO to change its currently existing cap on a generation resource’s incremental offer into the energy markets to the higher of each resource’s specific cost-based incremental energy offer and $1,000/MWh (the current cap in most RTOs/ISOs). FERC also proposed to allow cost-based energy offers above $1,000/MWh to set the Locational Marginal Price (LMP) received by all generators that clear the market. However, under FERC’s proposal, the Market Monitoring Unit (MMU) or the RTO/ISO would be required to verify the costs comprising such a cost-based incremental energy offer before that offer could be used to calculate LMPs.

In Order No. 831, FERC adopted all of these proposals, directing each RTO/ISO to revise its current market rules to cap each resource’s incremental energy offer at the higher of $1,000/MWh or the resource’s MMU or RTO/ISO-verified, cost-based incremental energy offer. FERC also required that such offers, if verified by the MMU or RTO/ISO, be used to calculate the market clearing price received by all resources supplying energy. 

In an important change from the proposed rule, however, FERC also directed the RTOs/ISOs to adopt a “hard cap” on cost-based incremental energy offers at $2,000/MWh.  While the regulations adopted in Order No. 831 still allow generators to recover any verified costs that they incur above $2,000/MWh, the hard cap will prevent those resources from setting the market clearing price. If dispatched, such generators would instead receive an uplift payment to recover the difference between the market clearing price and their verified costs. 

Order No. 831 is arguably FERC’s most significant step to date in its ongoing efforts to improve “price formation” in the RTO/ISO markets. FERC states that its final reforms to the offer caps will “make it more likely” that market clearing prices will reflect the true marginal cost of production when short-run marginal costs exceed the $1,000/MWh caps currently in place in most RTOs/ISOs. The Commission acknowledges  that the inclusion of the $2,000/MWh hard cap may “diminish the ability [of the Final Rule] to address the shortcomings of current offer caps,” since it sets a limit on the ability of market prices to rise above that level even when generators with higher marginal costs are dispatched to provide energy. But FERC nonetheless concludes that the limits of the cost verification process – in particular, the practical difficulties of reliably verifying costs in advance in all circumstances – require that a cap be in place to protect customers.  

As noted above, these reforms should allow the energy market clearing prices received by all generators (and other resources providing energy) to rise when the marginal unit’s costs exceed $1,000 per MWh. How often that occurs, and how much additional overall revenue will accrue to electric generators (especially the merchant generation sector), remains to be seen. In addition, how the RTOs/ISOs each implement the required cost verification processes will be critical and will bear watching closely, since cost verification is required for the higher marginal cost offers to set the clearing price. Order No. 831 leaves the details of such processes – which could, like other market mitigation issues, prove controversial – to the RTOs/ISOs to develop in the first instance in their compliance filings.

Order No. 831 will become effective 75 days after it is published in the Federal Register.  RTO/ISO filings to revise their tariffs to comply with the rule will be 75 days after it becomes effective.

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.