FERC Proposes Allowing Higher Priced Energy Offers in Organized Markets

Jan 25, 2016

Reading Time : 3 min

Specifically, FERC is proposing that each RTO/ISO change its currently existing cap on a generation resource’s incremental offer into the energy markets to the higher of each resource’s specific cost-based incremental energy offer or $1,000/MWh (the current cap in most RTO/ISOs). If this change is implemented, cost-based energy offers above $1,000/MWh would be eligible to set the Locational Marginal Price (LMP) received by all generators that clear the market. However, the Market Monitoring Unit (MMU) or the RTO/ISO would be required to verify the costs comprising such a cost-based incremental energy offer before that offer could be used to calculate LMPs.

In the NOPR, the Commission preliminarily finds, pursuant to Section 206 of the Federal Power Act,1 that the hard cap on incremental energy offers of $1,000/MWh that currently exists in all of the RTOs/ISOs, except PJM Interconnection, L.L.C., (PJM) (which recently revised its hard cap to $2,000/MWh), may no longer be just and reasonable. The Commission voiced a number of concerns with the status quo, driven largely by multiple requests for waivers of the cap that were submitted by PJM, the New York Independent System Operator (NYISO) and the Midwest Independent Transmission System Operator in the past few years to address concerns that generators facing high gas prices during cold weather events would fail to recover their actual costs due to the offer cap. However, FERC is clear that its proposal would apply to any resource facing short-run marginal costs in excess of $1,000/MWh, and not only gas-fired generators.

The Commission’s concerns are not confined to a potential that generators with must-offer obligations will be unable to recoup their costs during extreme weather events, however. The Commission is also concerned that the offer cap will encourage generators that lack a must-offer commitment to choose not to run when they are most needed. FERC also expressed concerns that the cap can affect price formation by suppressing LMPs. LMPs suppressed below the marginal cost of production send an inaccurate signal to load as to the actual cost of electricity, and to resources regarding the value of the next increment of supply. Finally, the cap can result in inaccurate signals to the RTO/ISO itself, since the RTO/ISO cannot observe the cost differences among resources that are bidding at $1,000/MWh and thus may not dispatch those resources most efficiently.

Although FERC has concluded that a hard cap of $1,000/MWh may be unjust and unreasonable, it also concluded that it is unwise to lift the cap altogether, because of the role that it plays as a backstop to protect consumers if market power mitigation measures fail.

The Commission has asked for comments on a number of issues related to the proposal, including:

  • whether there should be a hard cap on cost-based energy offers for the purposes of calculating LMPs, and whether that cap should equal $2,000/MWh (as it currently does in PJM) or some other number
  • whether RTOs/ISOs have the ability to verify the costs embedded in cost-based incremental offers prior to the day-ahead and real-time market clearing process, and whether it is also necessary to verify physical cost components
  • whether the RTO/ISO or its MMU may need additional information to ensure that costs that are difficult to quantify, such as opportunity costs, are accurately reflected in a cost-based energy offer, and whether the use of an adder is appropriate for cost-based offers of more than $1000/MWh
  • whether the RTO/ISO or its MMU may need additional information or new authority to require currents to a cost-based energy offer to ensure that that offer accurately reflects the resource’s short-run marginal costs
  • whether excluding virtual transactions above $1,000/MWh could have undesirable consequences
  • the impact of the proposal on RTO/ISO seams.

1 16 U.S.C. § 824e.

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.