FERC Proposes Landmark Penalty for Alleged Energy Efficiency Resource Capacity Market Manipulation

January 8, 2025

Reading Time : 5 min

By: Stephen J. Hug, Emily P. Mallen, Ben N. Reiter, Sharmila P. Das, Scott Daniel Johnson, Barbara Deathe (Senior Paralegal Specialist)

On December 16, 2024, the Federal Energy Regulatory Commission (FERC or the Commission) issued an Order to Show Cause and Notice of Proposed Penalty proposing to assess staggering civil penalties against American Efficient, LLC and its affiliates (collectively, American Efficient) in connection with an alleged scheme to manipulate the capacity markets operated by PJM Interconnection, L.L.C. (PJM) and the Midcontinent Independent System Operator, Inc. (MISO).1 The Order directs American Efficient to show cause as to why it should not be required to pay a civil penalty of $722 million and disgorge $253 million.2

The Order arises from an investigation that was commenced in 2021 to evaluate the participation of American Efficient in the MISO and PJM markets as “Energy Efficiency Resources” (EER). Until recently, both MISO and PJM permitted entities to participate in their capacity markets as EERs and receive capacity payments for committing to reducing demand.3 Under the MISO and PJM tariffs, EERs were required to (i) reduce electricity use, (ii) maintain a nexus to end-use customer projects and (iii) either own or hold contractual rights to such projects in order to qualify for capacity payments.4

The Order alleges that American Efficient violated these tariff requirements by bidding EERs into the capacity market reflecting its estimate of the demand reduction associated with the sale and installation of certain energy efficient products. According to the FERC Enforcement Staff Report (the Report) attached to the Order, American Efficient entered into program agreements with manufacturers, distributors and retailers of energy efficient products under which American Efficient agreed to pay its partners for data on the sales of energy efficient products to consumers. These agreements also purported to transfer title to the products’ environmental attributes from the program partner to American Efficient. According to the Report, American Efficient would then use the sales data to estimate the number of megawatts (MWs) of peak energy consumption that would be saved if end-use customers used the products as assumed in a future delivery year and then allocated those MWs to capacity zones within the market based on a retailer’s zip code. The Report claims, however, that American Efficient did not have any contractual relationships with the customers purchasing the products, did not provide product rebates or discounts to end-use customers and had no way of ensuring that its program caused changes in consumer behavior.5 The Report states that, because the program did not actually reduce electricity use and American Efficient did not own or hold contractual rights to the use of the products producing the projected energy savings, American Efficient was ineligible to participate in the PJM and MISO capacity markets as an EER.6 Enforcement staff further alleges that American Efficient “knowingly or recklessly misled” MISO and PJM by presenting what was effectively a “market research scheme” as a capacity resource and unjustly profited from the scheme to the tune of more than half a billion dollars.7

The Order gave American Efficient 30 days (since extended to 90 days, until March 17, 2025) to respond to the Commission’s allegations and show cause as to why it should not be found to have violated the Federal Power Act (FPA), FERC regulations and the MISO and PJM tariffs, and why the alleged violations should not result in the proposed disgorgement and civil penalty.8 It also requires American Efficient to choose between an immediate penalty assessment with the right to a jury trial in federal court and an administrative hearing before an administrative law judge prior to the assessment of the penalty, with any further right to a jury trial waived.9

The Order is notable in several respects. First, the magnitude of the proposed penalties dwarfs the penalties that FERC has proposed or assessed in enforcement actions in recent years. In fact, the civil penalties that FERC proposes to assess to American Efficiency represent approximately 80% of the total civil penalties that FERC has assessed in other enforcement actions between 2007 and 2024.10 American Efficient believes it is “the largest proposed penalty and disgorgement figure in the Commission’s history.”11 In recommending a civil penalty of $722 million, FERC Enforcement staff cited American Efficient’s decision to expand its market participation in PJM after having been disqualified from participating in the MISO and ISO New England Inc. capacity markets. This, according to FERC Enforcement staff, demonstrates that “American Efficient knowingly or recklessly misled the ISO/RTOs to gain entry and retain access to those markets.”12 FERC Enforcement staff also noted the significance of the violations, the involvement of high-level personnel in the allegedly manipulative scheme, the lack of any meaningful compliance program, and the failure of American Efficient to cooperate with FERC Enforcement staff’s investigation.

Second, the Order highlights FERC’s continued focus on pursuing enforcement actions against entities that commit to provide a product—such as capacity—when they do not have the capability to do so or that fail to meet their commitments.13 Although this has long been a focus of FERC’s enforcement efforts, these types of actions have become increasingly common in recent years as tightening supply conditions across FERC-jurisdictional markets have increased the potential economic and reliability consequences of non-performance.

Finally, the Order is notable in that FERC provides American Efficient with the option of electing to have a proceeding before an administrative law judge (ALJ) despite the Supreme Court’s decision in Jarkesy v. SEC,14 which held that the Securities and Exchange Commission’s (SEC) assessment of civil penalties through an adjudication before an ALJ violated the right to a jury trial guaranteed by the 7th Amendment. FERC previously terminated proceedings before an ALJ in a longstanding FERC enforcement action following the issuance of the Court’s decision in Jarkesy and indicated that it would be issuing a further order clarifying FERC’s view on the implications of the Court’s holding.15 Because Jarkesy concerned whether the 7th Amendment “permits the SEC to compel respondents to defend themselves before the agency,”16 it may be that FERC views the voluntary election of a proceeding before an ALJ as not implicating the issues raised in Jarkesy. However, the Order directs American Efficient to choose from these procedural paths without offering further comment on the court’s ruling.


1 American Efficient, LLC, 189 FERC ¶ 61,196 (2024) (Order), available at: https://elibrary.ferc.gov/eLibrary/filedownload?fileid=5DC48F13-EB3B-CC57-94DC-93D040E00000.

2 Id. at P 2.

3 On November 5, 2024, FERC approved PJM’s proposal to remove EERs from its capacity market following the 2025/2026 Delivery Year. PJM Interconnection, L.L.C., 189 FERC ¶ 61,095 (2024). EERs can still participate in the MISO capacity market.

4 See, e.g., Order at P 3.

5 See Report at 2.

6 See id.

7 Id. at 2, 41, and 146.

8 Id., Ordering Paras. (A)-(D); Am. Efficient, LLC, Notice of Extension of Time, Docket No. IN24-2-000 (Dec. 26. 2024).

9 Order at P 4 and Ordering Para. (F).

10 See FERC, All Civil Penalty Actions – 2025 (stating that FERC has assessed a total of approximately $885 million in civil penalties since 2007), available at: https://www.ferc.gov/civil-penalties/all-civil-penalty-actions-2025.

11 Am. Efficient, LLC, et al., Unopposed Motion of Respondents to Extend Answer Deadline at 2, Docket No. IN24-2-000 (filed Dec. 26, 2024).

12 Report at 146.

13 See, e.g., Big Rivers Elec. Corp., Docket No. IN24-9-000; Vista Energy Storage, LLC, Docket No. IN24-11-0000; Ketchup Caddy, LLC and Philip Mango, Docket No. IN23-14-000; Todd Meinershagen, Docket No. IN23-4-000; FERC v. Silkman, et al., No. 1:16cv00205 (D. Maine).

14 SEC v. Jarkesy, 144 S. Ct. 2117 (2024).

15 Total Gas & Power North Am., Inc., et al., 188 FERC ¶ 61,197 (2024).

16 Jarkesy, 144 S. Ct. at 2125.

Share This Insight

Previous Entries

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

Speaking Energy

January 23, 2025

Under a second Trump presidency, the U.S. is expected to consider reversal of many of the Biden administration’s climate and environmental policies, in addition to a markedly different approach to trade policy and oil & gas regulation. This includes expanding oil & gas development on public lands and offshore, lifting the pause on liquified natural gas (LNG) exports to non-Free Trade Agreement countries and repealing the methane fee.

...

Read More

Speaking Energy

January 15, 2025

We are pleased to share a recording of Akin’s recently presented webinar, “Drilling Down: What Oil & Gas Companies Can Expect from Federal Agencies During Trump’s Second Administration.”

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.