FERC Proposes to Require Wind Generators to Supply Reactive Power, Seeks Comment on Compensation Methods

Nov 23, 2015

Reading Time : 3 min

In Order No. 661 (issued in 2005), FERC exempted wind plants from this obligation,1 finding that unlike traditional generators, wind generators must install additional costly equipment to provide reactive power capability. FERC concluded that this additional cost would unduly burden wind generation and present an obstacle to its growth.

Earlier this year, however, FERC allowed PJM Interconnection, L.L.C., to revise its tariff (under the “independent entity variation” standard) to require wind generators interconnecting to its system to have the capability to provide reactive power.  FERC found that PJM’s proposal would not present a barrier to the development of wind generation, given improvements in wind power technology and the declining cost of providing reactive power capability.

FERC relies on similar reasoning in its November 19, 2015, proposal, preliminarily concluding that advances in wind turbine technology have lowered the costs to wind plants to provide reactive power capability, and that as a result, requiring such capability is not the obstacle to wind power development that it was when Order No. 661 was adopted. Given such cost declines, FERC posits that continuing to exempt wind generators from the requirement to provide reactive power unduly discriminates against other types of generation that must shoulder the burden of supplying reactive power. In addition, FERC expresses concern that as wind power becomes a larger part of the generation mix and other types of generation supplying reactive power retire, exempting wind plants from the obligation to provide reactive power capability could cause reliability issues, especially in local areas with high wind penetrations.

Under the proposal, all newly constructed wind generators interconnecting to the transmission grid under the jurisdiction of FERC (including any wind plants that have an unexecuted interconnection agreement pending at FERC at the time the requirement takes effect) would be required to have the capability to provide reactive power service when their real power output exceeds 10 percent of nameplate capacity. FERC also proposes to require existing wind generators to possess such capability if they undertake upgrades that require a new interconnection agreement. 

How wind generators are compensated for providing reactive power could be a significant issue in this proceeding. FERC notes that under its proposal wind generators would be eligible to be paid for providing reactive power capability just like other generators, based on the cost of providing such capability.  FERC acknowledges, however, that “the cost to a wind generator of providing reactive power may not be easily estimated using existing methods that are applied to [other] generators.” While compensation is not explicitly part of FERC’s proposal here, the agency is seeking comment on whether existing methods for determining reactive power compensation are appropriate for wind plants, and if not, whether alternative methods should be used.

Compensation for reactive power service has been on FERC’s radar for some time. Last year, FERC staff released a report reviewing existing and alternative approaches to reactive power compensation, and held a workshop exploring these and related issues. The record developed there may be relied on by FERC if it ultimately decides to address compensation in this rulemaking proceeding.

Other issues that may garner significant comment include FERC’s proposal to apply reactive power requirements to existing wind generators undertaking upgrades that require a new interconnection agreement, and its proposal to require wind plants to provide reactive power when operating above 10 percent of their nameplate capacity. These proposals differ in some respects from the PJM tariff revisions approved earlier this year. Specifically, PJM’s reactive power requirements do not apply to any wind plant uprates, and only require wind plants to provide reactive power when operating above 25 percent of their nameplate capacity.

Comments on FERC’s proposal are due 60 days after publication in the Federal Register.


1 Order No. 661 allows a transmission provider to require a wind plant to provide reactive power capability only if it shows, in a system impact study, that such capability is necessary to ensure safety or reliability.

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.