FERC Rejects Electric Generators’ Request to Adopt Centralized Capacity Market in California

Dec 11, 2018

Reading Time : 5 min

On November 19, 2018, FERC denied the complaint in full—not only declining to mandate a centralized capacity market, but also declining to order any more granular reforms or even to study the issue further through a technical conference.

California’s Resource Adequacy Regime

Unlike the three Eastern organized electricity markets (PJM Interconnection, L.L.C.; ISO New England Inc.; and the New York Independent System Operator), CAISO does not use a centralized resource adequacy procurement process (e.g., a capacity auction) to ensure adequate system capacity and reliability. The reasons for this—and the complex nature of resource planning and capacity procurement in California—are rooted in California’s history and its status as a single-state wholesale market that is subject to both federal oversight by FERC (through CAISO) and state energy policies and initiatives.

CAISO and the California Public Utilities Commission (CPUC) address resource adequacy principally through bilateral, near-term contracting between LSEs and generators. In brief, LSEs are required to contract with generators for a “Resource Adequacy” (RA) capacity product. RA is intended to ensure that LSEs have sufficient capacity to meet their peak load plus a reserve margin. RA contracts obligate the generator owner to make the resource available for dispatch in the CAISO energy market.   

For various reasons, the RA program has been viewed by many as flawed and has led to RA prices that are often too low to adequately compensate certain existing natural gas-fired generators needed by CAISO to run its system. Generators claim that state policies promoting the development of certain types of preferred generation resources, and a lack of alignment between resources that LSEs can use to meet RA requirements and those that CAISO actually needs to run its system, have increasingly resulted in LSEs not securing capacity commitments from specific generators that are needed by CAISO. These developments have affected existing natural gas-fired generators in particular since they rely on the RA market to compensate them for their capacity and, in many cases, are needed by CAISO to operate the grid reliably. Unlike newly built generators, existing generators are not eligible under state policy to be included in Investor-Owned Utilities’ Long-Term Procurement Plans (LTPPs), which effectively prevents them from obtaining substantially higher, longer-term capacity payments. This is because existing generators are already presumed to be available when assessing additional resource needs through the LTPP process. While such resources may be presumed to be available, in fact, insufficient RA revenues can jeopardize their continued operation. As a result, CAISO has increasingly needed to rely on “last-resort,” out-of-market mechanisms to secure capacity from generators that could not sell RA capacity at sufficient prices to sustain operations.

The Complaint Proceeding

On June 20, 2018, La Paloma, which owns a 1,124 MW natural gas generating facility in McKittrick, California, filed a complaint against CAISO alleging that CAISO’s tariff is unjust, unreasonable and unduly discriminatory as it relates to resource adequacy. Premised on the failure of the RA market to send accurate price signals that can attract and retain resources that are needed for reliability, La Paloma urged FERC, as a remedy, to implement a centralized resource adequacy procurement process like those used in the Eastern markets (i.e., a capacity market with centralized, uniform locational pricing and other key features).

While the complaint was filed by a single generator, it garnered broad support from other generators and proponents of competitive markets. On August 24, 2018, the Electric Power Supply Association, a trade association representing independent power producers, filed comments supporting the complaint and the implementation of a centralized capacity market. The Western Power Trading Forum also filed comments supporting the complaint. Calpine, a major independent power producer, filed comments supporting La Paloma’s claim that the CAISO tariff is unjust and unreasonable as it relates to resource adequacy, but proposed, as a remedy, comprehensive reform of CAISO’s backstop capacity procurement mechanisms, which it viewed as more realistic than a centralized capacity market given the nature of the California market. CAISO, along with various LSEs and public interest groups, opposed the complaint.

FERC’s November 19, 2018 Order

In its November 19 order, FERC denied La Paloma’s complaint in full. FERC’s basis for denying the complaint was technical: that La Paloma failed to identify any specific provisions of CAISO’s FERC-approved tariff that were not just and reasonable as is required in a complaint under Section 206 of the Federal Power Act. FERC found that CAISO’s resource adequacy processes were crafted to respect the role of state and local regulatory authorities over resource procurement. FERC found that La Paloma failed to demonstrate that circumstances surrounding the bifurcated framework and division of responsibilities over resource adequacy in California had changed such that this division of responsibilities was unjust and unreasonable or that it has resulted in CAISO not being able to ensure sufficient capacity to operate the grid reliably. FERC rejected La Paloma’s arguments regarding the insufficiency of revenues in the CAISO market, finding that La Paloma did not demonstrate that existing generators are systematically denied the opportunity to recover their costs or that revenue insufficiency will lead to the premature retirement of needed resources. 

FERC also noted that La Paloma did not identify any reliability violations resulting from alleged inadequacies of CAISO’s resource adequacy paradigm and found that evidence of CAISO’s increased use of backstop capacity procurement mechanisms does not demonstrate a reliability concern or failure of the resource adequacy paradigm to attract and retain flexible capacity. In addition, FERC found that La Paloma’s claim that California’s LTPP program unduly preferences renewable resources and discriminates against existing generation was not legally cognizable because it focused on state-administered programs and not CAISO’s tariff. Finally, FERC rejected requests by various generators to convene a technical conference on the issue of resource adequacy in California, finding that potential resource adequacy reforms were being appropriately considered through the CAISO stakeholder process and CPUC proceedings.

Implications

Complaints about California’s wholesale electricity market and capacity procurement process are nothing new. Historically, FERC has been reluctant to take action that could be viewed as interfering with the state’s energy policy objectives and resource planning process, instead relying on market changes to be considered through CAISO stakeholder processes and CPUC proceedings. In its complaint, La Paloma sought to place the alleged flaws in California’s capacity procurement process squarely before FERC to resolve. La Paloma (and other generators) may have hoped that a newly constituted FERC might be more willing than prior Commissions to consider such grievances, particularly given the Commission’s focus, in other contexts, on resource adequacy from a grid reliability and resiliency standpoint, and the impact of state policies on wholesale markets.

FERC’s actions in denying the complaint outright suggest that its overall approach to regulation of the California market as it relates to resource adequacy issues might not differ much from prior Commissions. For various reasons, many thought it unlikely that FERC would attempt to mandate a centralized capacity market in California; FERC’s rejection of that request was perhaps the least notable part of its order. Rather, the manner in which FERC denied the complaint was significant. In particular, by denying generators’ request for a technical conference (which would not bind FERC into taking any action or initiating any proceedings) and endorsing stakeholder processes and state regulatory proceedings as the appropriate forums to consider reforms, FERC appears to be signaling that it will continue to take a deferential approach to California resource adequacy issues. Further, the substance, tone and outcome of the order, considered together, suggest that FERC is not concerned about what many consider to be a problem of current regulatory policies failing to send the right market signals to spur needed competitive generation in California, which could have longer-term, negative impacts on grid reliability and energy prices.

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.