FERC Seeks Information from RTOs/ISOs on Hybrid (Generation + Storage) Resources

Jan 21, 2021

Reading Time : 1 min

By: Shawn Whites (Energy Regulatory Specialist)

FERC’s directive seeks to build the record on potential challenges and barriers to hybrid resource participation in the wholesale power markets, and follows its July 2020 technical conference on the topic, which we addressed here. FERC explained that RTOs/ISOs “are currently undertaking work to address the increase in hybrid resources” in their regions, and several have requested that FERC “allow such work to continue before taking additional action.”3 PJM Interconnection, L.L.C., for example, formed a new subcommittee last year to “identify operational and market enhancements needed to accommodate” the “more than 13,000 MW” of solar-plus-storage projects in its interconnection queue.4 Meanwhile, FERC recently accepted tariff revisions from the California Independent System Operator designed to serve as “an initial step toward developing more robust rules and models to integrate [hybrid] resources and optimize their performance.”5

Should RTO/ISO reports and public comments indicate that barriers exist, FERC’s next step could be a rulemaking proposing similar reforms to those adopted for energy storage and distributed energy resources in Order Nos. 841 and 2222.6


1 Hybrid Resources, 174 FERC ¶ 61,034, at P 1 (2020).

2 Id. P 3.

3 Id.

4 PJM Interconnection, L.L.C., New Subcommittee Focuses on Hybrid Resource Needs, PJM Inside Lines (Aug. 6, 2020), https://insidelines.pjm.com/new-subcommittee-focuses-on-hybrid-resource-needs.

5 Cal. Indep. Sys. Operator Corp., 173 FERC ¶ 61,146, at P 2 (2020).

6 See Elec. Storage Participation in Mkts. Operated by Reg’l Transmission Orgs. and Indep. Sys. Operators, Order No. 841, 162 FERC ¶ 61,127 (2018), order on reh’g and clarification, Order No. 841-A, 167 FERC ¶ 61,154 (2019); Participation of Distributed Energy Resource Aggregations in Mkts. Operated by Reg’l Transmission Orgs. and Indep. Sys. Operators, Order No. 2222, 172 FERC ¶ 61,247 (2020). 

Share This Insight

Previous Entries

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Midcontinent Independent System Operator, Inc. (MISO) directing MISO and MISO transmission owners to show cause as to why MISO’s tariff should not be found to be unjust and unreasonable (Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 23, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to PJM Interconnection, L.L.C. directing PJM and PJM transmission owners to show cause as to why PJM’s tariff should not be found to be unjust and unreasonable (PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (the Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 22, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued an order to Southwest Power Pool, Inc. (SPP) directing SPP and SPP transmission owners to show cause as to why SPP’s tariff should not be unjust and unreasonable (Southwest Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (Order)) because it fails to sufficiently:

...

Read More

Speaking Energy

June 18, 2026

On June 18, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued show cause orders under section 206 of the Federal Power Act to PJM Interconnection, L.L.C. (PJM), Midcontinent Independent System Operator, Inc. (MISO), Southwest Power Pool, Inc. (SPP), California Independent System Operator Corporation (CAISO), ISO New England Inc. (ISO-NE) and New York Independent System Operator, Inc. (NYISO), together with their transmission owners, directing each region to justify or reform the tariff provisions governing how data centers and other large loads connect to and receive service from the transmission grid. The orders are part of FERC’s broader response to rapidly increasing electricity demand, particularly from data centers and other large loads, and advance the objectives of the Secretary of Energy’s October 2025 Advance Notice of Proposed Rulemaking (ANOPR) by seeking to accelerate “speed to power” while preserving grid reliability, affordability and consumer protections. 

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.