First Circuit Decision Finds No Private Right of Action Under PURPA Against a Utility

Nov 21, 2017

Reading Time : 3 min

Background

Allco Renewable Energy Limited owns 11 solar QFs in Massachusetts and wanted to sell the output to Massachusetts Electric Company d/b/a National Grid. As implemented by the Federal Energy Regulatory Commission’s (FERC) regulations, PURPA generally requires that utilities purchase the output of QFs at the utility’s “avoided cost.” National Grid offered to purchaseAllco’s power under its standard contract, which offered to payAllco the spot market rate for power.2 Allco petitioned the Massachusetts Department of Public Utilities (DPU) to investigate the reasonableness of National Grid’s offer, which did not conform to Allco’s understanding of PURPA. The DPU denied Allco’s petition, finding that National Grid’s rate was consistent with its regulations.

Allco then petitioned FERC to bring an enforcement action against the DPU on the grounds that the DPU’s regulations conflicted with FERC’s regulations implementing PURPA, which FERC declined to do. When FERC declines to bring an enforcement action, the aggrieved QF may file an enforcement action in federal district court. Allco then filed suit against the DPU and National Grid in the District of Massachusetts, seeking a declaration from the district court that National Grid had a “legally enforceable obligation” to purchase the output of Allco’s QFs—in addition to damages for lost income. The district court found that the DPU’s regulations were inconsistent with PURPA, but dismissed Allco’s claims against National Grid on the grounds that Allco did not have a private right of action to enforce National Grid’s obligation to purchase its QFs’ output.  

First Circuit Decision

The 1st Circuit upheld the district court’s dismissal ofAllco’s claims against National Grid and, in so doing, rejected the argument that PURPA implied an enforcement route against a utility outside of the express statutory scheme. The court summarized what it described as PURPA’s “intricate enforcement framework,” which authorizes three types of enforcement actions: (1) by FERC in federal court challenging the implementation of PURPA by the states, (2) by QFs in state or federal court challenging the implementation of PURPA by the states or (3) by QFs in state court challenging how a utility has applied state-implemented PURPA regulations.3 Focusing on the first two types of actions, PURPA does allow a QF to sue a state regarding its implementation of PURPA in federal court, but only if it first petitions FERC to enforce the statute and FERC declines to do so. However, PURPA’s statutory framework does not permit a QF to sue a utility in federal court to enforce the statute’s must-buy obligation. Instead, a QF seeking relief under PURPA may only (a) file a complaint against the utility at the state commission and then challenge any adverse decision by the state commission in state court, or (b) petition FERC to bring an implementation challenge against the state and, if FERC declines, then sue the state in federal court.4

In its decision, the 1st Circuit relied on extensive Supreme Court precedent that private rights of action under federal law cannot be “created by mere implication, but must be unambiguously conferred.”5 The court also observed that the existence of express provisions of PURPA governing enforcement also “cut against” a private right of action.6 Finally, the Court pointed to FERC’s role in enforcing the statute, observing that a provision providing a potential “administrative remedy” also speaks against a private right of action.7 

The 1st Circuit’s decision clarifies the narrow and specific nature of a QF’s rights under PURPA.8 Although a remedy exists for a QF to enforce a utility’s obligations, the QF must rely on the mechanisms that the statute provides, rather than take its dispute directly to federal court.


1 Allco Renewable Energy Ltd. v. Mass. Elec. Co., No. 17-1296 (1st Cir. Nov. 13, 2017) (“Nov. 13thDecision”).

2 Allco Renewable Energy Ltd. v. Mass. Elec. Co., 208 F. Supp. 3d 390, 395 (D. Mass. 2016).

3 Nov. 13thDecision at 5-6.

4 Id. at 17. 

5 Id. at 11 (internal quotations omitted).

6 Id.

7 Id. at 11-12.

8 The 1st Circuit, relying on much of the same reasoning, also concluded that the Federal Power Act does not provide a private right of action against a utility. Id. at 19-20.

Share This Insight

Previous Entries

Speaking Energy

January 15, 2025

We are pleased to share a recording of Akin’s recently presented webinar, “Drilling Down: What Oil & Gas Companies Can Expect from Federal Agencies During Trump’s Second Administration.”

...

Read More

Speaking Energy

January 9, 2025

On January 6, 2025, the Federal Energy Regulatory Commission (FERC) issued a Final Rule to amend its regulations governing the maximum civil monetary penalties assessable for violations of statutes, rules and orders within FERC’s jurisdiction. The Final Rule is a result of the Federal Civil Penalties Inflation Adjustment Act Improvements Act of 2015, which requires each federal agency to issue an annual inflation adjustment by January 15 for each civil monetary penalty provided by law within the agency’s jurisdiction. The adjustments in the Final Rule represent an increase of approximately 2.6% for each covered maximum penalty. FERC’s adjusted maximum penalty amounts, which will apply at the time of assessment of a civil penalty regardless of the date on which the violation occurred, are set forth here and will become effective upon publication in the Federal Register.

...

Read More

Speaking Energy

January 9, 2025

Join projects & energy transition partners Ike Emehelu and Shariff Barakat as well as climate change partner Ken Markowitz at Infocast's Projects & Money, where Ike will moderate the "The State of Project Finance – View from the C-Suite" panel, and Shariff will moderate the "Capital Markets & Other Capital Sources for Project Finance & Investment" panel. Ken will moderate the “Carbon Markets Forecast for 2025” panel.

...

Read More

Speaking Energy

January 8, 2025

On December 16, 2024, the Federal Energy Regulatory Commission (FERC or the Commission) issued an Order to Show Cause and Notice of Proposed Penalty proposing to assess staggering civil penalties against American Efficient, LLC and its affiliates (collectively, American Efficient) in connection with an alleged scheme to manipulate the capacity markets operated by PJM Interconnection, L.L.C. (PJM) and the Midcontinent Independent System Operator, Inc. (MISO).1 The Order directs American Efficient to show cause as to why it should not be required to pay a civil penalty of $722 million and disgorge $253 million.2

...

Read More

Speaking Energy

December 5, 2024

On November 27, 2024, the Federal Energy Regulatory Commission issued Venture Global CP2 LNG, LLC, an order that sets aside, in part, the Commission’s prior authorization of the CP2 LNG Terminal and CP Express Pipeline Project (collectively, the CP2 Project) under sections 3 and 7 of the Natural Gas Act (NGA). 

...

Read More

Speaking Energy

December 5, 2024

On November 27, 2024, in Venture Global, CP2 LNG, LLC,1 the Federal Energy Regulatory Commission’s (FERC or Commission) explicitly overruled precedent set in Northern Natural Gas Co.,2 a 2021 decision in which FERC made an affirmative finding that an interstate natural gas pipeline project it was certificating under section 7 of the Natural Gas Act (NGA) would not make a “significant” contribution to global climate change. Northern Natural is the only FERC decision in which a so-called significance determination was made with respect to greenhouse gas emissions (GHG) arising from a FERC-regulated natural gas infrastructure project. In Venture Global, FERC rejected arguments that it needed to follow Northern Natural and assess the significance of GHG emissions in all NGA certificate proceedings to comply with the National Environmental Policy Act (NEPA). NEPA requires federal agencies, including FERC, that perform “major federal actions,” which include issuing NGA section 7 certificates, to prepare an environmental impact statement (EIS) if the action will “significantly affect[] the quality of the human environment.”3 FERC has been under pressure to fully explain why it has chosen not to apply Northern Natural’s significance analysis in subsequent cases, and that issue is currently before FERC on remand from the U.S. Court of Appeals for the District of Columbia (D.C. Circuit) in Healthy Gulf et al. v. FERC, which reviewed FERC’s approval of a liquefied natural gas (LNG) terminal under NGA section 3.

...

Read More

Speaking Energy

December 4, 2024

On November 21, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued Order No. 1920-A1 addressing requests for rehearing and clarification of FERC’s landmark final rule on transmission planning and cost allocation issued in May 2024. While the Commission largely affirmed the final rule, the order grants rehearing of some of the more controversial aspects of Order No. 1920.

...

Read More

Speaking Energy

November 26, 2024

We are pleased to share a recording of Akin’s recently presented webinar, “Post-Election Outlook for the Energy Sector.”

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.