Lack of Quorum Costs East Kentucky Power Cooperative in PURPA Dispute

Sep 15, 2017

Reading Time : 3 min

By: Shawn Whites (paralegal)

The Public Utility Regulatory Policies Act of 1978 (PURPA), a 1970s law that sought to foster the development of independent power producers and renewable generation, requires electric utilities to buy power at “avoided cost” from QFs.1 Pursuant to FERC’s Order No. 688, however, utilities may seek authorization from FERC to terminate this purchase requirement prospectively for QFs that have nondiscriminatory access to a wholesale electricity and capacity market. Importantly, any such termination does not apply to “legally enforceable obligations” between a QF and the utility that exist prior to the filing of the utility’s application seeking termination of the purchase requirement.

On November 4, 2016, EKPC submitted its initial application seeking to terminate the purchase requirement in its service territory for QFs of more than 20 MW.  PURPA and FERC’s regulations require the Commission to make a final determination within 90 days of the application’s filing date. Due to the lack of quorum at the Commission, however, the Commission was unable to act on the filing within 90 days.  FERC issued a notice in March 2017 noting as much and deemed the application denied. EKPC resubmitted the application in March, but FERC, still lacking a quorum, deemed the application denied once again in June when the 90-day period expired. EKPC filed a third and final application in June 2017, which FERC approved in the September 2017 Order.

While FERC grantedEKPC’s June 2017 application, it held that termination of the purchase requirement was effective June 9, 2017—the date of the third and final application—and not the date ofEKPC’s initial application, November 4, 2016, asEKPC requested. Bluebird Solar LLC and Blue Jay Solar LLC, two QFs inEKPC’s territory, informedEKPC of their intention to sell their output toEKPC pursuant to PURPA prior to June 9. FERC therefore concluded thatEKPC’s application “does not foreclose Bluebird or Blue Jay from having established a legally enforceable obligation under PURPA.”1  Barring any state law restrictions, FERC concluded that Bluebird and Blue Jay “would be grandfathered such that Commission approval of [the] Application would not include Bluebird or Blue Jay QFs.”2  Had the Commission approved the original (and nearly identical) EKPC application from November 2016, the two QFs would not have received grandfathered status because the original application preceded the QFs’ legally enforceable obligations.

The 90-day requirement in the PURPA statute states that FERC “shall make a determination” on any such application within 90 days, but it does not state—in contrast to certain provisions in the Federal Power Act—that inaction within that period automatically results in denial (or approval).  EKPC sought rehearing of FERC’s notice deeming the application denied, but the Commission dismissed the request because, according to FERC, the notice does not constitute a final Commission order subject to rehearing. 

In other PURPA news, FERC issued an order granting QF certification last week to the Beaver Creek Wind II, LLC and Beaver Creek Wind III, LLC facilities located in Stillwater County, Montana. The utility required to purchase the output of the QFs, NorthWestern Corp., had protested the application, arguing that the facilities are each within one mile of other affiliated Beaver Creek Wind projects and that, based on the Commission’s “one-mile rule,” the facilities exceed the 80 MW limit for QF status.4 While this proceeding appeared to provide FERC with an opportunity to clarify its methodology for applying the one-mile rule, FERC ultimately declined to provide clarification because it found that Beaver Creek II and Beaver Creek III are neither affiliates of each other nor the other Beaver Creek projects located in close proximity.

 


1 QFs are small, renewable generation facilities and cogeneration facilities.

2 September 2017 Order at P 21.

3 Id.

4 To determine whether two or more facilities are located at the same site, FERC’s regulations specify that a facility located within one mile of the facility for which QF status is sought—as measured by the distance between the electric generating equipment of the facilities—is deemed to be located at the same site.  18 C.F.R. § 292.204(a)(2).  Thus, two 80 MW facilities owned by affiliates would not qualify as separate QFs if they are located within one mile of each other.

Share This Insight

Previous Entries

Speaking Energy

April 15, 2025

On April 9, 2025, President Trump issued an executive order (EO)1 directing several federal agencies and subagencies that regulate energy, environmental, and conservation matters,2 including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), to establish conditional sunset dates for “regulations governing energy production.” The stated objective of the EO is to require agencies to periodically reexamine their regulations to ensure that they continue to serve the public good. For FERC, the order covers regulations promulgated under the Federal Power Act (FPA), the Natural Gas Act (NGA) and the Powerplant and Industrial Fuel Use Act (FUA)3, as amended, while DOE must consider regulations promulgated under the Atomic Energy Act (AEA), the National Appliance Energy Conservation Act, the Energy Policy Act of 1992 (EPAct 1992), the Energy Policy Act of 2005 (EPAct 2005) and the Energy Independence and Security Act of 2007 (EISA), as amended (collectively the Covered Regulations).4 To the extent the DOE has been directed to promulgate regulations under various sections of the NGA, FPA and FUA, and FERC has been directed to promulgate regulations specific to the statutes attributed to the DOE in the EO, the EO is silent. The EO expressly does not apply to those “regulatory permitting regimes authorized by statute.”5

...

Read More

Speaking Energy

April 10, 2025

On April 8, 2025, President Trump issued an Executive Order (EO) directing the Department of Energy (DOE) to take steps to expand the use of its emergency authority under Federal Power Act (FPA) Section 202(c) to require the retention of generation resources deemed necessary to maintain resource adequacy within at risk-regions of the bulk power system regulated by the Federal Energy Regulatory Commission (FERC).1 The EO appears to envision a more active role for DOE in overseeing and supporting the resource adequacy of the grid that deviates from the historic use of Section 202(c) and touches on issues at the intersection of state and federal authority over resource planning.

...

Read More

Speaking Energy

March 10, 2025

On March 5, 2025, the United States Department of Energy (DOE) approved Golden Pass LNG Terminal LLC’s (GPLNG) request to extend a deadline to begin exporting liquefied natural gas (LNG) from its terminal facility currently under construction in Sabine Pass, Texas for 18 months, from September 30, 2025, to March 31, 2027 (the Order). The Order amends GPLNG’s two existing long-term orders authorizing the export of domestically produced LNG to countries with which the United States does and does not have free trade agreements (FTA).1  The Order does not amend the authorizations’ end date, which remains December 31, 2050. Under section 3 of the Natural Gas Act (NGA), the DOE may authorize exports to non-FTA countries following completion of a “public interest” review, whereas exports to FTA countries are deemed to be in the public interest and the DOE is directed to issue authorizations without modification or delay.

...

Read More

Speaking Energy

March 4, 2025

Join projects & energy transition partner Shariff Barakat at Infocast’s Solar & Wind, where he will moderate the “Tax Equity Market Dynamics” panel.

...

Read More

Speaking Energy

February 13, 2025

Oil & gas companies continue to identify and capitalize on opportunities related to the deployment of new energy technologies, with their approaches broadly maturing and coalescing around maximizing synergies, leveraging available subsidies and responding to regulatory drivers.

...

Read More

Speaking Energy

February 11, 2025

On January 30, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) approved a Stipulation and Consent Agreement (Agreement) between the Office of Enforcement (OE) and Stronghold Digital Mining Inc. (Stronghold) resolving an investigation into whether Stronghold had violated the PJM Interconnection, L.L.C. (PJM) tariff and Commission regulations by limiting the quantity of energy made available to the market to serve a co-located Bitcoin mining operation.1 This order appears to be the first instance of a public enforcement action involving co-located load and generation and comes at a time when both FERC and market operators2 are scrutinizing the treatment of co-located load due to the rapid increase in demand associated with data center development.

...

Read More

Speaking Energy

February 5, 2025

2024 was about post-consolidation deal flow and a steady uptick in activity across the oil & gas market. This year, mergers & acquisitions (M&A) activity looks set to take on a different tone as major consolidation plays bed down.

...

Read More

Speaking Energy

January 30, 2025

The oil & gas industry is experiencing a capital resurgence, driven by stabilizing interest rates and renewed attention from institutional investors. Private equity is leading the charge with private credit filling the void in traditional energy finance and hybrid capital instruments gaining in popularity. Family offices are also playing a crucial role, providing long-term, flexible investments.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.