Second Circuit Denies Request to Stay NYISO’s New Capacity Zone

Jun 6, 2014

Reading Time : 2 min

NYISO itself took the unusual position of refusing to support either side.  It filed an amicus brief that expressly stated that NYISO supported neither party. NYISO sought to inform the court only that the issuance of a stay would require that it modify its complex auction software. NYISO stated that it would not be able to remove the NCZ from its calculations in the available time frame, though it would be able to do so before the next round of auctions begins on November 1, 2014. NYISO believed that it would be able to approximate the results of an auction without the NCZ in place if it were called upon to do so, but that it would have to request a tariff waiver from FERC to implement that solution. As an alternative, NYISO suggested that, if the court wished to order a stay, it could do so effective in November, by which point NYISO would be able to remove the NCZ from its software.

FERC’s Rehearing Order denied requests to delay or phase in the NCZ. It did grant rehearing on a narrow issue related to the ability of certain suppliers to withhold capacity, and it ordered NYISO to delete a provision in its tariff that could have been used to implement a withholding strategy. FERC declined to order NYISO to establish tariff rules for eliminating the NCZ if the deliverability issues that created it are resolved, but urged NYISO to address the issue through its stakeholders.

The 2nd Circuit’s order was extremely short.  It denied the request for a writ of mandamus as moot and denied the motions for an emergency stay by citing to the relevant standard.2 The court did not choose to explain which aspects of the standard the petitioners failed to satisfy. A longer order from the 2nd Circuit may be forthcoming, however, since the same parties have already petitioned the court for review of FERC’s Rehearing Order. They have not requested a stay.


1 New York Indep. Sys. Operator, Inc., 144 FERC ¶ 61,126 (2013); New York Indep. Sys. Operator, Inc., 146 FERC ¶ 61,043 (2014).

2 See In re World Trade Ctr. Disaster Site Litig., 503 F.3d 167, 170 (2nd Cir. 2007) (“The four factors to be considered in issuing a stay pending appeal are well known: ‘(1) whether the stay applicant has made a strong showing that he is likely to succeed on the merits; (2) whether the applicant will be irreparably injured absent a stay; (3) whether issuance of the stay will substantially injure the other parties interested in the proceeding; and (4) where the public interest lies.’”)

Share This Insight

Previous Entries

Speaking Energy

April 23, 2026

On April 15, 2026, the Federal Energy Regulatory Commission (FERC or the Commission) issued one of the largest enforcement penalty orders in its history, finding that American Efficient, LLC (American Efficient) and its affiliates engaged in a decade‑long fraudulent scheme involving offering energy efficiency resources (EERs) over which they had no contractual authority into the PJM Interconnection, L.L.C. (PJM) and Midcontinent Independent System Operator, Inc. (MISO) capacity markets.1

...

Read More

Speaking Energy

April 7, 2026

Oil & gas companies are adapting swiftly to the administration’s energy dominance agenda, replacing net zero commitments with strategic opportunities across three emerging revenue streams. The AI-driven data center boom is fueling unprecedented demand for reliable onsite power, with traditional energy companies leveraging their natural gas resources and infrastructure expertise to build dedicated generation facilities and enter construction joint ventures. Major oil producers are simultaneously exploiting their subsurface exploration capabilities to expand into critical mineral supply chains essential for battery technologies, electronics and aerospace applications. 

...

Read More

Speaking Energy

April 3, 2026

Akin is proud to serve as a Gold Sponsor of Infocast’s Tax Credits & Transferability 2026, taking place on May 5-6 in Houston.

...

Read More

Speaking Energy

March 26, 2026

Antitrust enforcement is showing early signs of transformation as new leadership promises more accommodating approaches to oil & gas consolidation. In the United States, Federal Trade Commission chair Andrew Ferguson assumed office in January 2025, signaling a more permissive stance toward merger approvals that oil & gas companies have welcomed enthusiastically. This shift represents a potential departure from the heightened scrutiny that characterized previous years, creating optimism among dealmakers seeking opportunities for strategic combinations. 

...

Read More

© 2026 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.