Shiny, Happy NEPA: How the Administration Plans to Make NEPA More User-Friendly

Jan 13, 2020

Reading Time : 3 min

In particular, CEQ is proposing to consolidate the definition of “effects,” eliminating its references to indirect and cumulative effects with the goal of restraining courts from reading those terms so expansively as to include speculative effects, resulting in time-consuming litigation and delay. CEQ also proposes to change how effects should be interpreted, to be more in line with the Supreme Court’s opinion in Public Citizen, 541 U.S. 752, such that the effects must (1) have a reasonably close causal relationship to the proposed action or alternatives; (2) not be remote in time or geography; and (3) not include effects that the agency has no authority to prevent or would happen without the agency action.

One effect, if not the primary aim, of these proposed definitional changes is the exclusion of climate change considerations from NEPA reviews—lead agencies need only assess impacts tied directly to a project and not downstream impacts on climate or greenhouse gas emissions. This would streamline the analysis of certain large projects such as the Keystone XL pipeline, the construction of which has relatively little direct, immediate climate impact regardless of the overall impact facilitated by its operation.

Another key change would revise the definition of “major Federal action,” a threshold requirement for NEPA application, to projects receiving a certain level of federal funding or requiring federal agency approval. The proposed definition specifically does not include “nondiscretionary decisions made in accordance with the agency’s statutory authority” or “non-Federal projects with minimal Federal funding or minimal Federal involvement where the agency cannot control the outcome of the project.” In particular, the proposed rule notes that an example of a project that could be exempt from NEPA is an infrastructure project where a small percentage of federal funding goes to the design of the project, but the project is otherwise funded with private or local funds. These changes could significantly curtail the number of projects undergoing NEPA review.

Also of note, the proposed rule would narrow the range of alternatives that must be considered by defining the term reasonable alternative as “a reasonable range of alternatives” and those that are “technically and economically feasible and meet the purpose and need of the proposed action.” The proposed rule, while highlighting the role of participating agencies and the public, would restrict legal challenges by providing that “comments not timely raised and information not provided shall be deemed unexhausted and forfeited.”

Announcement of CEQ’s proposed changes sparked immediate reaction by key policy makers in Congress. In the House of Representatives, a bipartisan pair of Members—Reps. Diana DeGette (D-CO) and Frances Rooney (R-FL)—circulated a letter to their House colleagues urging opposition to the administration’s proposal that “ignores the full extent of the climate crisis.” Rep. Debbie Dingell (D-MI)—wife of the late Rep. John Dingell (D-MI), a principal architect of NEPA—vowed legislative action to halt or reverse the proposed changes, possibly through use of the Congressional Review Act (CRA) procedure to block implementation of a final rule. Rep. Raul Grijalva (D-AZ), chair of the House Committee on Natural Resources, which has jurisdiction over NEPA, expressed similar concerns. Key Democratic Senators—including Sen. Tom Carper (D-DE), the ranking member on the Senate Committee on Environment and Public Works (EPW), which has jurisdiction over NEPA—voiced strong opposition to the proposed rule.

On the other hand, Sen. John Barrasso (R-WY), chair of the Senate EPW Committee, applauded the administration’s proposal, stating “[t]he Trump administration is taking common sense steps to make the National Environmental Policy Act work better for the American people.” Sen. Lisa Murkowski (R-AK), chair of the Senate Committee on Energy and Natural Resources, also welcomed the effort to “propose a modernization of federal environmental review and permitting processes under [NEPA].” Similarly, the ranking Republican on the House Natural Resources Committee, Rep. Rob Bishop (R-UT), lauded the administration’s efforts to fix “America’s broken environmental review and permitting process.”

Given the central role and long history of NEPA in environmental reviews of major federal actions, Congress likely will conduct detailed oversight of the rulemaking process. Given the timing of this announcement less than 10 months before presidential and congressional elections, the issue likely will receive significant policy and political attention this year, and into the next administration and Congress in 2021.

EPA is accepting comments on the proposal until March 10, 2020, and has scheduled public hearings in Denver and Washington on February 11 and 25, 2020, respectively. Project proponents should generally welcome the changes as they will limit the number of projects subject to NEPA review and are crafted to streamline and expedite the review process for those projects still needing review. Others, however, may see a significant downside in an attempt to eliminate from federal consideration the climate impact or greenhouse gas emissions of projects. Regardless of one’s position, ignoring climate effects may turn out to be a bridge too far, for what would otherwise be another lauded deregulatory action from the current administration.

Share This Insight

Previous Entries

Speaking Energy

December 5, 2024

On November 27, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued Venture Global CP2 LNG, LLC,1 an order that sets aside, in part, the Commission’s prior authorization of the CP2 LNG Terminal and CP Express Pipeline Project (collectively, the CP2 Project) under sections 3 and 7 of the Natural Gas Act (NGA). In anticipation of future appellate challenges to its authorization of the CP2 Project, FERC ordered the initiation of a supplemental environmental impact statement (SEIS) process under the National Environmental Policy Act (NEPA) to assess the CP2 Project’s contribution to cumulative air impacts for nitrogen dioxide (NO2) and particulate matter less than 2.5 micrometers (PM2.5). Accordingly, FERC stated that it would not allow construction to commence on the CP2 Project’s proposed liquefied natural gas (LNG) export terminal and related feed gas pipeline until the SEIS process concluded and a subsequent order was issued. Concurrent with its Venture Global order, FERC issued a projected schedule for the NEPA process that does not conclude until July 24, 2025. Construction on the CP2 Project had been expected to be imminent, with the project sponsor seeking a partial authorization to proceed with construction only hours prior to Venture Global’s issuance.

...

Read More

Speaking Energy

December 5, 2024

On November 27, 2024, in Venture Global, CP2 LNG, LLC,1 the Federal Energy Regulatory Commission’s (FERC or Commission) explicitly overruled precedent set in Northern Natural Gas Co.,2 a 2021 decision in which FERC made an affirmative finding that an interstate natural gas pipeline project it was certificating under section 7 of the Natural Gas Act (NGA) would not make a “significant” contribution to global climate change. Northern Natural is the only FERC decision in which a so-called significance determination was made with respect to greenhouse gas emissions (GHG) arising from a FERC-regulated natural gas infrastructure project. In Venture Global, FERC rejected arguments that it needed to follow Northern Natural and assess the significance of GHG emissions in all NGA certificate proceedings to comply with the National Environmental Policy Act (NEPA). NEPA requires federal agencies, including FERC, that perform “major federal actions,” which include issuing NGA section 7 certificates, to prepare an environmental impact statement (EIS) if the action will “significantly affect[] the quality of the human environment.”3 FERC has been under pressure to fully explain why it has chosen not to apply Northern Natural’s significance analysis in subsequent cases, and that issue is currently before FERC on remand from the U.S. Court of Appeals for the District of Columbia (D.C. Circuit) in Healthy Gulf et al. v. FERC, which reviewed FERC’s approval of a liquefied natural gas (LNG) terminal under NGA section 3.

...

Read More

Speaking Energy

December 4, 2024

On November 21, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued Order No. 1920-A1 addressing requests for rehearing and clarification of FERC’s landmark final rule on transmission planning and cost allocation issued in May 2024. While the Commission largely affirmed the final rule, the order grants rehearing of some of the more controversial aspects of Order No. 1920.

...

Read More

Speaking Energy

August 7, 2024

*Thank you to JaKell Larson, 2024 Akin Summer Associate, for her valuable collaboration on this article.

...

Read More

Speaking Energy

July 31, 2024

Interstate oil, liquid and refined products pipelines regulated by the Federal Energy Regulatory Commission (FERC) will soon be able to raise their transportation rates (provided they were set using FERC’s popular Index rate methodology) in the wake of a significant new decision by the District of Columbia Circuit (the D.C. Circuit) in Liquid Energy Pipeline Association v. FERC (LEPA).

...

Read More

Speaking Energy

July 29, 2024

On Wednesday, July 24, 2024, the U.S. House of Representative Committee on Energy and Commerce held a Subcommittee on Energy, Climate, and Grid Security hearing to review the Federal Energy Regulatory Commission (FERC or Commission) Fiscal Year 2025 Budget Request. Members of the Subcommittee had the opportunity to hear testimony from all five Commissioners, including FERC Chairman Willie Phillips and Commissioner Mark Christie, as well as the three recently confirmed commissioners, David Rosner, Lindsay See and Judy Chang. In addition to their prepared remarks, the five commissioners answered questions on FERC’s mandate to provide affordable and reliable electricity and natural gas services nationwide, while also ensuring it fulfills its primary mission of maintaining just and reasonable rates.

...

Read More

Speaking Energy

July 29, 2024

On July 9, 2024, the U.S. Court of the Appeals for the D.C. Circuit held that the Federal Energy Regulatory Commission (FERC or the Commission) erred in ordering refunds for certain bilateral spot market transactions in the Western Energy Coordinating Council (WECC) region that exceeded the $1,000/megawatt-hour (MWh) “soft” price cap for such sales.1 Finding FERC failed to conduct a “Mobile-Sierra public-interest analysis” before “altering” those contracts by ordering refunds, the court vacated FERC’s orders and remanded the case to FERC for further proceedings.2

...

Read More

Speaking Energy

July 8, 2024

On June 28, 2024, in Loper Bright Enterprises v. Raimondo, the U.S. Supreme Court overruled Chevron U.S.A. Inc. v. Natural Resources Defense Council, Inc., which for 40 years required court deference to reasonable agency interpretations of federal statutes in certain circumstances, even when the reviewing court would read the statute differently. The Court ended “Chevron deference” and held that courts “must exercise their independent judgment in deciding whether an agency has acted within its statutory authority.” In doing so, the Court upended a longstanding principle of administrative law that is likely to make agency decisions more susceptible to challenge in the courts.

...

Read More

© 2024 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.